OUR PROJECTS

As a leading Logistic service provider- ACK POWER TECHNOLOGY LTD your one-stop solution for all mechanical and electrical needs.

We are committed to facilitating efficient and reliable transactions for various industries. With our extensive network and expertise, right now we specially aim to optimize your gas trading supply chain, enabling seamless operations and maximizing productivity.

GHORASHAL PALASH UREA FERTILIZER PROJECT [GPUFP]

ACK Power Technology Ltd. proudly contributed to the Ghorashal Palash Urea Fertilizer Project (GPUFP) as a trusted sub-contractor under China National Chemical Engineering and Construction Corporation Seven Co., Ltd. (CC7). This project is owned by Bangladesh Chemical Industries Corporation (BCIC), with Mitsubishi Heavy Industries Ltd. as a key partner.

What We Delivered:

  • Fabrication and installation of Knock Down Tanks, including:
    • Oil Tanks
    • Boiler Water Tanks
    • Underground Tanks
  • Piping and Ducting systems.
  • Steel Structures and Conveyor Systems installation.
  • Renovation of the old warehouse, including:
    • Electrical works.
    • Civil works.
  • Fabrication and installation of Liquid Ammonia Receiving Piping Systems.
  • Raw Water Intake Pre-Filter installation, including:
    • Civil works.
    • Piping works.
    • Electrical works.

Our team handled these tasks with great care and professionalism while strictly maintaining all safety protocols.

ACK Power Technology Ltd. is proud to be part of this significant project that plays a vital role in supporting Bangladesh’s chemical and fertilizer industry.

Bibiyana 400MW Combined Cycle Power Plant Project

ACK Power Technology Ltd. worked as a proud subcontractor for Larsen & Toubro (L&T) at the Bibiyana 400MW Combined Cycle Power Plant in Sherpur, Sylhet. From 2017 to 2019, ACK Power Technology Ltd. successfully completed several important jobs, including:

  • Building Structure Erection for STG (Steam Turbine Generator) and GTG (Gas Turbine Generator).
  • Piping Work for STG and GTG.
  • Electrical Cable Tray Installation and Cable Pulling & Assembly.
  • Insulation Work and Commissioning Tasks.

ACK Power Technology Ltd. did the job with great care, sticking to all safety rules and meeting the project’s deadlines. The team worked professionally to ensure everything was completed perfectly.

Our years of experience and attention to detail helped make this project a big success!

Shikalbaha 225 MW Dual Fuel CCPP, Chittagong, Bangladesh

Between April 2016 and February 2018, ACK Power Technology Ltd. worked as the Mechanical Sub-Contractor for Union Mercantile Ltd. (UML) on the Mechanical Works of L&T at the Shikalbaha 225 MW Dual Fuel Combined Cycle Power Plant (CCPP) in Chittagong, Bangladesh. Our team handled a variety of critical mechanical works across multiple systems and buildings, ensuring the project was completed on time with the highest quality and safety standards.

B.O.P. Works:

Civil and Structural Works:

  • DM Plant: Erection of civil structure.
  • Chemical House: All piping and equipment installation, including CPVC, SS, and CS piping.
  • Deep Bore Well System: All CS piping installation.
  • HRSCC Round Tank: All GRP pipelines.
  • Sprinkler System: Installation for Diesel Engine Driven Firewater Pump and Diesel Tank.
  • Clarified Water Pump House: Civil structure erection.
  • Service Water System: CS pipeline from B.O.P. to Pump House.

Building and Equipment Installation:

  • Gas Booster & Air Compressor Building: Civil structure erection.
  • Circulating Water Pump House: Structure erection.
  • G.T.G. Transformer: All firefighting system piping installation.
  • S.T.G. Transformer: Firefighting pipeline installation.
  • Gas Line: Gas Booster to Gas Turbine piping work.
  • Workshop Building: Structure erection and equipment installation.
    • Overhead Cranes: Erection and installation for both the workshop building and gas booster.

Piping and System Installation:

  • HRSG Piping: Installation work.
  • Air Instrument System: GI pipeline work.
  • Service Water: CS piping installation.
  • Effluent Transfer System: CPVC piping installation.

Third Triangle Area Works:

  • Fuel Oil Pipeline: Pontoon to HSD Tank (CS piping).
  • Firefighting & Foam Line: Pump House to HSD Tank – all piping installation.
  • Pump House: Structure erection and all equipment installation.

Our Commitment

ACK Power Technology Ltd. delivered all aspects of this large-scale power plant project with efficiency and attention to detail. Our dedicated team ensured the proper execution of mechanical works, from structural erection to the installation of piping and equipment, making sure every component worked seamlessly to support the operation of the Shikalbaha CCPP.

This project highlights our expertise in handling diverse mechanical works for power plants, further strengthening our reputation as a trusted mechanical sub-contractor in large industrial projects.

200 MW & 115 MW HFO Power Plants – Jamalpur & Mymensingh

In September 2018, ACK Power Technology Ltd. successfully completed a range of fabrication, erection, and mechanical works for the 200 MW and 115 MW HFO Power Plants in Jamalpur. The project was undertaken for United Power Generation Distribution Co. Ltd., with fabrication works carried out at the Ashulia Fabrication Yard and subsequent installation at the project sites in Jamalpur and Mymensingh.

Key Works Completed:

Duct Systems

  • Fabrication and erection of Hot Air Ducts and their supports.
  • Exhaust Duct Fabrication, including:
    • Horizontal Exhaust Duct Alignment (EGM Bellows, Support Cutting, Welding, and Alignment).
    • Silencer Installation & Alignment.
    • Pad Support Structure and Cantilever Support Structure.
    • Tee and Elbow fittings, welding, and erection.
    • Expansion Bellows and Flange Fitting.
    • Stopper fabrication and installation.

Structures

  • Fabrication and erection of:
    • Pipe Rack Structures.
    • Boiler Structures.
    • LP Drum Structures.
    • Deaerator, Flash, and Feed Water Tank Structures and their alignment.
    • Platform Support Bridges.
    • Silencer Base Plates.
    • Column Anchor Base Plates (cutting, rod fitting, and welding).

Piping Systems

  • Cooling Water Filling Pipeline and supports, including motor, valve, and fittings installation.
  • Impulse Pipes for PT, LT, and FT Piping, including valve, level transmitter, pressure gauge, and condensate pot erection.

Tank Fabrication

  • Condensate Tank and BDT Tank Fabrication.

Other Structures

  • Completion of HFO Separator Room and Compressor Room.

Our Commitment

ACK Power Technology Ltd. carried out all tasks with precision, maintaining strict safety protocols and ensuring high-quality delivery within the agreed timeline.

This project demonstrates our expertise in steel structure fabrication, piping systems, and mechanical works, showcasing our ability to handle complex projects with efficiency and professionalism.

300 MW HFO Power Plant Project – Anowara, Chittagong

ACK Power Technology Ltd. successfully completed a range of critical fabrication, erection, piping, and mechanical works for the 300 MW HFO-based Power Plant in Anowara, Chittagong, for United Power Generation Distribution Co. Ltd. This project involved several key tasks, which were carried out with precision and efficiency.

Key Activities Completed:

  • Steel Structures

    • Fabrication and erection of EGM Structures.
    • Fabrication and erection of Exhaust Ducts and Exhaust Duct Fittings.
    • Hot Air Duct fabrication and erection.
    • Duct Support Structures (ranging from 5 to 13 EGM) fabrication and erection.
    • Fabrication and erection of Boiler Base Plates and Base Plates with Anchor Bolts.
    • Silencer Structure fabrication and erection.
    • Fabrication and erection of Feed Water Tank Structures.
    • Earthing Bar fabrication and erection.
    • Staircase and Platform fabrication and erection.
  • Piping and Mechanical Works

    • Fabrication, alignment, and erection of various piping lines.

Our Commitment to Excellence

ACK Power Technology Ltd. ensured that all tasks were executed following strict safety standards, while maintaining high levels of quality and timely completion. Our experienced team worked efficiently to meet project goals, delivering essential components for the power plant’s successful operation.

This project reflects our capability in handling large-scale power plant construction, especially in areas like steel structure fabrication, ductwork, and complex piping systems.

Mechanical Works for ETB Plan at Epyllion Group, Banglabazar, Rajandrapur, Gazipur

Between June 2015 and February 2016, ACK Power Technology Ltd. worked as the Mechanical Sub-Contractor for MM Engineering on the ETB Plan Mechanical Works for Epyllion Group at their facility in Banglabazar, Rajandrapur, Gazipur.

Key Activities Completed:

  • Provided mechanical support for the ETB Plan project, including key installations, maintenance, and other essential mechanical works.
  • Worked closely with MM Engineering to ensure timely and efficient project execution while maintaining high standards of quality and safety.

This project showcases ACK Power Technology Ltd.’s experience and expertise in providing mechanical solutions for large industrial projects, ensuring successful collaboration and project completion.

Rampal 1320 MW Coal-Fired Power Station Project

The Rampal Power Station, a 1320 MW coal-fired power station, is currently under construction at Rampal Upazila, Bagerhat District, Khulna, Bangladesh. This significant project is being led by the Main Contractor, Bharat Heavy Electricals Ltd (BHEL), with Power Mech serving as a Sub-Contractor.

Our Role in the Project

ACK Power Technology Ltd. is proud to be working under Power Mech on the conveyor system for this large-scale power plant. Our dedicated team is responsible for the following key tasks related to the conveyor system:

  • Erection of the conveyor system
  • Shedding and painting of components

Scope of Work

  • Conveyor System Erection: Ensuring proper installation of conveyor components, supporting the transportation of materials throughout the plant.
  • Shedding and Painting: Applying protective coatings to the conveyor components to prevent corrosion and ensure durability over time.

ACK Power Technology Ltd. is committed to maintaining high standards of quality and safety while contributing to the successful completion of this vital power generation project.

Pontoon and Jetty/Gangway Work – Sreepur 163 MW Power Plant

ACK Power Technology Ltd. successfully completed the Fabrication, Erection, Sand Blasting, Painting, Launching, and Testing work of Pontoon and Jetty/Gangway as a Sub-Contractor under MAX Infrastructure Ltd. for the Sreepur 163 MW Power Plant Project.

What We Delivered:

  • Fabrication and Erection of Pontoon and Jetty/Gangway structures
  • Sand Blasting and Painting of components to protect them from corrosion and wear
  • Launching and Testing of completed structures to ensure full operational readiness

ACK Power Technology Ltd. successfully completed this project while maintaining strict adherence to safety protocols and high-quality standards. Our team ensured timely completion and effective execution of the work, contributing to the successful development of the Sreepur 163 MW Power Plant.

60 Ton Fuel Tank Fabrication & Erection – Lub House Industries Ltd.

ACK Power Technology Ltd. successfully completed the 60 Ton Fuel Tank Fabrication & Erection works, including Materials Supply and Civil Works, as a Sub-Contractor under MAX Infrastructure Ltd. for Lub House Industries Ltd., located at BSCIC Industrial Estate, Kararchar, Narsingdi.

What We Delivered:

  • Fabrication and Erection of a 60 Ton Fuel Tank
  • Materials Supply for the construction and installation of the tank
  • Civil Works related to the tank’s foundation and support structures

ACK Power Technology Ltd. carried out this project with professionalism, ensuring all aspects of the fabrication and erection were completed in compliance with safety protocols. The project was successfully delivered on time, contributing to the operational needs of Lub House Industries Ltd.

Contact Us

If you have any query, please furnish your requirements in below
Please enable JavaScript in your browser to complete this form.
Name

Email

info@ackpowerbd.com

Phone

+8801731008186

Location

1st Floor, H-841, R-19, K-Block Bashundhara, Dhaka.

Social Media: